Every payment structure protects one party at one point in the order, then stops. A deposit protects the supplier's material exposure; the balance protects the buyer's leverage until the goods are proven; a documentary credit protects both sides against a payment that fails on paperwork, and neither against a product that fails on inspection. Most payment disputes between importers and Chinese suppliers are not about honesty but about which protection the buyer believed they had bought. The useful question is not what terms you can get, but at which stage you can still inspect, and whether the money moves after that stage.

Where the risk actually sits

Stage of the order What is exposed Term that gives the buyer a remedy here
Deposit paid, production not started The deposit None. Supplier selection and a written order protect you
Material committed, goods in production The balance and the schedule Stage inspection tied to a release condition
Goods finished, not shipped The supplier's finished stock Balance against a pre-shipment inspection certificate
In transit Title and the document set Balance against a bill of lading the buyer controls
After arrival Whatever inspection missed Claim window written into the purchase order

A term that moves money earlier than your last inspection point removes your remedy, whatever discount is attached.

T/T deposit and balance: what the buyer really holds

Telegraphic transfer in two parts is the default in Chinese export trade for an administrative reason: it needs no bank facility on either side, and both parties can see the money arrive.

The deposit buys capacity: a supplier who has received nothing has no reason to reserve machine time or buy brass, while one whose deposit covers material and the first run has reason to start. That is why a token deposit produces a slow order rather than a cheap one.

The balance buys the document set. Once the goods are packed and the container booked, the supplier holds a bill of lading that is the only lawful way to collect the cargo at destination. Paying the balance against a copy of that bill keeps the document in the supplier's hands until the money is confirmed, which is the buyer's strongest position in the transaction. It disappears the moment the buyer accepts a telex release before payment, or agrees the originals can be couriered "in parallel". After that the buyer is unsecured and the goods are at sea.

Paying against photographs of packed cartons is not verification. A photograph proves the cartons exist, not what is inside them, and not whether the plating passed a salt-spray check.

Documentary credit: documents, not defects

A letter of credit under UCP 600 runs on a principle that surprises first-time buyers: banks deal in documents, not goods. The issuing bank examines the presented documents and pays if they comply with the credit. It does not inspect the cargo.

The rules fix the mechanics. A bank has five banking days after presentation to examine the documents and give notice of refusal, and documents must be presented within the credit's validity. Each discrepancy is a refusal, a fee and a delay. Examiners work from ISBP, worth reading before you draft the credit.

A credit protects the payment pathway: it converts "will this supplier return my money if the goods are wrong" into "will the documents match the credit". If quality is the real risk, the credit must carry an inspection document from a named body, with the standard and the sampling plan written into it. A credit asking only for an invoice, packing list and bill of lading pays against paperwork and proves nothing about the cargo.

D/P and D/A: the bill of lading is the collateral

Documents against payment releases the set only when the buyer pays, so the buyer cannot take delivery without paying. The remaining exposure is the supplier's: if the buyer refuses the documents, the goods sit at a foreign port with freight and demurrage running.

Documents against acceptance is a different instrument in similar clothes. The buyer obtains the documents by accepting a bill of exchange, a promise to pay later. The supplier has extended credit and holds an accepted draft rather than cash. Buyers treat D/A as "D/P with a delay"; suppliers treat it as unsecured lending.

Both depend on the bill of lading being consigned to order and routed through banks. If the original set goes straight to the buyer's forwarder, D/P becomes an open account with extra paperwork.

Open account and platform escrow: who carries the risk

Open account means the supplier ships first and is paid later, so the risk sits with the supplier until the payment date, and the price carries it. It is extended after a payment history, not after a first enquiry.

Escrow through a trade platform is the middle structure: money is held by the platform and released when the buyer confirms receipt, or when a dispute is decided under platform rules. It protects the buyer's cash, but only within what those rules accept as evidence — a claim outside them fails whatever the goods are like. Read the dispute rules before treating the badge as a warranty.

Incoterms decide when payment is due, not just who pays freight

A payment term without an Incoterm is half a clause. "Balance before shipment" is clear under FOB, where the supplier's job ends when the container is on board. Under DDP the supplier still carries freight, clearance and duty after that payment clears, so the buyer has paid in full for goods that remain in the supplier's hands in transit.

Name the delivery point in the order and tie the payment trigger to it: against the bill of lading under FOB or CIF, against arrival and clearance documents under DAP or DDP. That alignment removes most of the arguments that follow a late container.

The documents that make a term enforceable

A structure is only as strong as its paperwork. Four items belong in the purchase order, and none costs anything at quotation.

  1. An inspection standard and sampling plan, so acceptance follows a rule rather than an opinion. ISO 2859-1 supplies the schemes; the acceptable quality limit is yours to set.
  2. The inspection point named in time — before packing, after packing, at loading — and who performs it.
  3. The document set the balance is released against, including whether an inspection certificate and test report are part of it.
  4. A claim window that outlives the balance payment, with the remedy stated: replacement in the next shipment, a credit note, or a debit against a retained amount.

The last item is the one that gets dropped. If the claim window closes the day the balance is paid, the term has handed all the risk to the buyer at the moment the buyer loses leverage.

Matching the structure to the relationship

On a first order with a supplier you have not audited, keep a measurable amount at risk until you have seen the goods, and put the inspection document into the term. With a supplier who has a record, open account lowers the price because the financing stops being priced in. The structure should follow the evidence you hold.

The lines we ship under these terms are the ones we make: LT-21 brass basin faucets, BQ20151-Q brass floor drains and SZ-13-25 European style bibcocks are cast, machined and finished in our production, so the inspection point, document set and release condition can be agreed against a specific product instead of a category.